The days are counted from the day work began until finished. This includes week end and days not worked.

 

The inspection begins DAY 1

The engine work completed and the parts shipped. Engine mount, TR actuator bracket and nacelle inspection begins. Over wing exit outer skin and frame inspection completed. DAY 4

The interior has been removed and the floor board removal starts. DAY 5

The landing gear and under floor inspections in progress DAY9

This day has few pictures, we were all busy doing inspection to take many pictures DAY 12

The inspection is progressing DAY 15

The inspection is progressing DAY 25

The inspection is completed except for the function checks that can't be performed until the repairs are completed on the engines and landing gear. DAY 31